ROOF EDGE PROTECTION ASSEMBLY
Free End Installations

1 Refer to the project
drawing
2 Lay the first Post at
the start position
3 Attach a Run End Counterweight
assembly to the first Post
4 Position the second
Post
5 Attach a Counterweight
to the second Post
6 Position the third Post
7 Position the fourth
Post and attach a Counterweight
8 Drop handrail and kneerail
into cradle fittings
9 Repeat the procedure
until completion
10 Check that the maximum
spacing for posts is no greater than 2000mm
11 Check that the maximum
spacing for Counterweights is no greater than 4000mm
12 Check that there is
a Run End Counterweight and adjacent Counterweight at each end
of a run
|
|
Closed Installations
1
Refer to the project drawing
2
Lay the first Post at the start position
3
Attach a Counterweight to the first Post
4
Position the second Post
5
Position the third Post and attach a Counterweight
6
Drop handrail and knee rail into cradle fittings
7
Repeat the procedure until completion
8
Check that the maximum spacing for posts is no greater
than 2000mm
9
Check that the maximum spacing for Counterweights is no
greater than 4000mm